Construction of 100,000 Pyongyang Houses Suspended

[imText1]The construction of 100,000 homes in Pyongyang has been put on hold due to a lack of cement. According to a Daily NK source, the project is around 40 percent complete.

The year’s aim is to finish 35,000 households out of the total 100,000 planned for construction. Work is due for completion by 2012.

The North Korean authorities had planned to construct 20,000 houses along the railroad from the Ryongseong-district via Seopo in the Hyeongjesan-district to the Ryeokpo-district and 25,000 houses in the center of the city. The schedule for laying the foundations has been set for September this year with plastering and interior works running until the end of the year.

The frame work of the houses, expected to finish by September, have been suspended due to lack of cement and other materials. A source commented that, “It was planned that general construction of frame works would finish in September but exterior construction has been halted due to a lack of materials.”

The North’s authorities have attempted to supply materials through the Sangwon Cement Complex, the Chollima Steel Mill Complex and other factories across the country. Annual production of cement in North Korea amounts to 6.4 million tons, approximately 12 percent of South Korea’s. However this is not enough to fuel general construction of key facilities such as social infrastructure and military facilities.

Large scale power plant constructions such as the Heecheon Power Plant combined with the building of 100,000 houses in Pyongyang have meant the shortage of cement is particularly acute.

Last year the North established the Pyongkeon Development Investment Group, attracting 320 million dollars of foreign capital. According to the plan submitted by the Group, 300,000 tons of cement are needed for foundation work in March alone.

Chosun Shinbo, the publication of the Chongryon (General Association of North Korean Residents in Japan), reported the construction of 35,000 houses was started in September last year. Since then, old houses in the districts have been torn down and neighborhoods rezoned. In March, the foundations of the houses were laid and the exterior frame work was built but construction has made little progress throughout June due to low cement levels.

The 100,000 household construction project in Pyongyang has been led by Jang Sung Taek, Director of the Ministry of Administration of the Workers’ Party, later appointed as the Vice-chairman of the National Defense Commission earlier this year at the Supreme People’s Assembly.

A source reported that, “Jang Sung Taek ordered foreign currency earning organizations to procure cement and that even selling coal should be considered.”

North Korea launched the state project to construct 100,000 houses in Pyongyang as a symbol of completion of the strong and prosperous state as part of a three-year campaign. Additionally, this project has been advertised as an achievement of the successor, Kim Jong Eun. If the plan fails then it will be a blow to the succession. If construction is suspended completely in advance of the Delegates’ Conference, happening in September, the image of Kim Jong Eun could be damaged.